UCOR’s Deactivation and Demolition (D&D) teams at the Y-12 National Security Complex’s 561,000-square-foot Alpha-4 facility are making substantial progress in preparing the former uranium separation facility for deactivation. Building on achieving “cold & dark” status in August, crews have successfully completed sorting and segmenting 447 legacy containers ahead of schedule. These shipments of legacy waste…

UCOR constructing facilities at Y-12 to place workers closer to buildings

UCOR’s Y-12 D&D craft are constructing temporary facilities to place workers closer to the Beta-4 and Alpha-5 buildings. They’ve placed seven concrete pads to support electrical racks and equipment that will provide power to these temporary facilities, which will support upcoming deactivation and demolition work. Click the video link to view this work. https://youtu.be/sqY0BOFADWM?si=6KIXGeNrDe4jyi3P  

Crews use crane to upgrade piping at the Process Waste Treatment System

UCOR Nuc Ops continues piping replacement project

The UCOR Nuclear Operations team successfully replaced the J-2101 A/B/C Discharge to 3608 piping and components as part of the overall 2600 Piping Replacement Project. This system transports radiological water collected from various locations to ORNL Building 3608 for final processing. Crews are currently installing heat trace and insulation. This replacement is the tenth of…

Video thumbnail showing two workers doing water sampling

Groundwater sampling is performed on the Oak Ridge Reservation to ensure that the groundwater is not being negatively impacted by past operations. UCOR periodically performs sampling at ETTP Heritage Center and a former scrap yard site, called White Wing Scrap Yard, to monitor for environmental impacts. To see our groundwater sampling team in action, watch…

Decorative

Brokk remote demolition mockup helping prepare for hot cell work

UCOR’s deactivation team at ORNL performed the final mockup of the Brokk remote demolition unit as they simulated operations to be done in hot cell A at building 3026. The remotely operated equipment allows the team to significantly increase workers’ distance from potential hazards. The unit will allow workers to conduct significant deactivation work safely…