Crews preparing for Beta-4 deactivation
Pre-deactivation continues at Y-12’s Beta-4 facility. Crews completed a soil sampling plan and follow on soil sampling, a necessary step for future interior facility deactivation. Other activities include installation of shower trailers, the boundary control station, restroom facilities, and initiation of cold & dark planning.