Oak Ridge, Tenn. – The final truckload of debris from the K-25 Building demolition project was
shipped from East Tennessee Technology Park (ETTP) today.
The K-25 Building, located at the East Tennessee Technology Park (the former Oak Ridge
Gaseous Diffusion Plant), was built in 1943 as part of the Manhattan Project. At that time, K-25
was the world’s largest building under one roof. Demolition of the mile-long, U-shaped
structure was completed in December 2013. Since then, workers have focused on removing the
resulting demolition debris.
Because the final section of the building contained components that were contaminated with a
slow-decaying radioactive isotope called technetium-99, workers had to segregate the
contaminated components in the field. Workers simplified that process by painting the
components with higher contamination bright blue before demolition. These highercontamination
components were shipped off-site for disposal, with the remainder of the debris
going to the Environmental Management Waste Management Facility located on DOE’s Oak
Ridge Reservation.
“As this phase of the project is completed, it’s a good time to remember the many people who
were responsible constructing, operating, and demolishing this historically significant facility,”
said Mark Whitney, manager of the Oak Ridge Office of Environmental Management. “The
people who built K-25 under intense schedules, the operators who helped our nation succeed
through World War II and the Cold War, and the cleanup crews that were able to safely
demolish and transport waste from the Department’s largest-ever demolition project despite
challenges.”
The K-25 Building operated until 1964, producing enriched uranium for defense and
commercial purposes. During the past decades, as the facility deteriorated, its demolition was
considered among the highest priorities for the environmental cleanup program in Oak Ridge.
The K-25 Building demolition project began in December 2008, when Bechtel Jacobs Company
LLC started demolition of the west wing. URS|CH2M Oak Ridge LLC (UCOR) took over the
project in August 2011 and successfully completed demolition of the building’s east wing and
north end. Wastes that have been hauled from the site include 6,000 compressors, 3,000
converters, 187,000 cubic yards of steel, 3,800 miles of electrical conductors, and 1.2 million
cubic feet of asbestos insulation. In total, more than 460,000 cubic yards of K-25 waste have
been shipped for disposal.
“While this final load of waste was just one in thousands of shipments that have been made, it
represents so much more,” said Leo Sain, UCOR President and Project Manager. “A great deal
of planning and careful execution has allowed us to finish this project safely and ahead of
schedule, bringing a successful end to the largest demolition project DOE has ever undertaken.”
Although the K-25 Building is gone, the historical significance of the facility and the complex
remains. In compliance with the National Historic Preservation Act, in 2012, the Department
signed a Memorandum of Agreement with 12 signatory/consulting parties, which plans for
ways to commemorate and interpret the historic significance of the site. DOE’s Oak Ridge Office
of Environmental Management will construct an equipment building that recreates a scale
representation of the gaseous diffusion technology. In addition, the site will display equipment,
artifacts, oral histories, photographs and videos at a K-25 History Center on site.